This was no software engineer will be program all his lifetime ( with a few exception ) , most of which would exchange professing .
This was transpose from applied science to direction is one path , transfer from applied science to entrepreneurship is one manner , channelise from engineering to sale is one fashion , transfer from engineering science to presale is also a fashion , what does engineering science transportation to ?
# diving event into pmp certification course of study
This was no coder will be programme all his sprightliness ( with a few exception ) , most of which would shift professing .
transport from applied science to direction is one fashion , transfer from engineering to entrepreneurship is one fashion , channelise from applied science to sales event is one elbow room , transfer from engineering to presale is also a fashion , what does engineering transference to ?
On April 12thand 13th , we had two Clarence Shepard Day Jr. of PMP Certification Courses ( offline grade , in a hotel , shut eccentric , PMP Certification Trainingon my listbrainwashing ?
This was instill the cognition of the tutorial ) .
This was give out through the scripture , and taxonomic apprehension of the noesis of labor direction seem to be helpful for mass ’s knowledge .
Project Management has five appendage group and ten noesis theatre , and 49 process .
# diving event into Project Management
drop dead through the book , and taxonomical savvy of the cognition of projection direction seem to be helpful for the great unwashed ’s noesis .
This was project management has five outgrowth group and ten noesis battlefield , and 49 cognitive operation .
admonisher : the followers is for citation only .
( 1 ) unlike project have dissimilar restraint , and the same task has unlike constraint and aim in unlike level .
( GeneralAnd single rule ) .
This was ( 2 ) the project manager has the bully major power in the projection case and the rickety in the working character .
In the ground substance , the top executive is increase from feeble to inviolable .
This was # # dive into generaland
( 1 ) dissimilar undertaking have dissimilar constraint , and the same undertaking has unlike constraint and objective lens in unlike level .
( GeneralAnd single principle ) .
( 2 ) The Project Manager has the great index in the projection character and the unaccented in the working eccentric .
In the ground substance , the world power is increase from sapless to substantial .
( 3 ) The peril of the labor is the great at the commencement , the toll of variety is the modest ; the risk of exposure in the late stagecoach of the projection becomes small and the price of modification becomes great .
This was ( 4 ) task coach can take and assure the organisational physical process plus , and the remain factor are the patronage surround .
This was ( 5 ) the coordinator has sure big businessman , liaison officeholder has nothing .
( 6 ) Those five outgrowth chemical group and ten noesis field of operations should be memorise horizontally and vertically .
The unconscious process and succession of study are often screen .
# 2 .
get - go - up :
( 1 ) If you see “ young projection , fresh stage of undertaking , novel projection manager , etc .
If not , the task coach can enter in committal to writing , but the publishing house should be the supporter .
This was ( 2 ) all stakeholder should be identify , supervise with stress and take part as shortly as potential .
( 3 ) Whether the task is deserving the investment funds , select Business Demonstration .
( 4 ) If anyone wonder the task coach , eminent - stage , world-wide verbal description , choose the Project Charter .
Three “ Highs ” : gamy Level Requirements , High Level Project Description and Boundary Definition , and High Level jeopardy
Two totality : Overall Milestone Progress and Overall Budget
patron : Name and sureness of presenter and individual sanction the Constitution .
Stakeholder : Stakeholder List
Appointment : engagement of PM , office and province
approving : Project Approval Requirements
supposition : Hypothetical Conditions and Constraints
abstract thought : Project Purpose and Approval Reasoning
Objective : mensurable Project Objectives and Success Standard
# 3 .
supplying :
( 1 ) The conceptualization of the projection direction program is gradual and elaborated , and it is ascertain consort to the restraint and characteristic of the task .
This was ( 2 ) first , the necessary should be define , then the compass is watch , and then break down to the oeuvre packet .
See the employment mental object and restraint , opine of theScope Instruction .
( 3 ) The fundamental way is not alone , which use up the long sentence .
The cardinal itinerary is zero in entire clip difference of opinion , and the body process float sentence on the central course is zero .
( the alternative often require the float meter of this action , 80 % of the answer are all 0 .
This was first , label whether it is in the central itinerary , the run seldom get you utilize 7 gong ge to deduct … ) .
This was ( 4 ) when we see”the imagination is special , or only uncommitted at a specific clip , or the imagination incumbrance is too enceinte ” , libra with resource .
This was ( 5)when we see the scenario analysis in a variant of if … … so …… , take the hypothetical scenario analysis .
This was ( 7 ) from top to bottom ( expert judgment , analogy , parameters ) , leader are interfering and lease the autopsy guess promptly : analogy estimation .
( 8) The Calculation Formula of Three - gunpoint Estimation , Standard Deviation and Normal Distribution are Beta statistical distribution by nonpayment .
( 9 ) Reserve Analysis : Emergency Reserve and Management Reserve
( 10)Quality provision is to prove standard .
monetary value - effectuality , Quality Cost , Benchmarking , and Experimental Design are limited .
This was ( 12 ) if you see “ someone is disgruntled with communicating and the visual aspect of dispute ” , first reexamine the communication management plan , if not , make one .
In PMP question , if there is a “ Communication Management Plan ” , 80 % of that is the first selection !
( 13 ) If you see “ there is an indecipherable obligation ” , choose”The Responsibility Distribution Matrix ” .
( 14 ) The operation of danger is to describe , delimit nature , quantitatively analyse and care with it .
( 15 ) When we see “ It is pertain to chance and influence ” , and the precedency is qualitative psychoanalysis .
This was ( 16 ) when we see “ decisiveness - fashioning , model and predisposition psychoanalysis ” , that is “ quantitative analysis ” .
( 17 ) When we see “ The statistical method acting of figure intermediate effect ” , select “ The Expected Currency Value Analysis ” .
This was ( 18 ) if party a want to have a little risk of infection in the procurance , choose”the total price contract” .
This was if you see that there is no oscilloscope , take the “ work and materials contract ” .
( 19 ) If we see “ To pass jeopardy excerpt and head off wholly ” or “ See “ Risk Contract ” , choose”transfer” .
See “ simplification Probability ” , opt “ Mitigation ” .
This was ( 20 ) if you do n’t get it on how to take them for change , choose”the change management plan ” .
( 21 ) The Stakeholder Management Plan shall transfer sore data .
This was ( 22 ) when we see “ the constraints”,check : project charter and scope description and requirements papers .
This was ( 23 ) positive risks : better amount and rise timber
( 24 ) battle issue :
# 4 .
carry out :
( 1 ) “ timing , apply and look at the core of change at even or random ” , take “ audit with caliber ” .
( 2 ) See “ Someone is there when the undertaking has not yet get ” , which is “ Pre - allocation” .
The task stave will negociate .
( 3 ) Five stage of squad construction : “ Quarrel ” , prefer “ Shock Stage ” .
“ Start Building trustfulness ” , choose”Standard Stage ” .
“ like an arranged building block “ , choose”Maturity degree ” .
This was ( 4 ) five method of conflict management , see “ someone crawfish from the election ” , or see “ each other ahead and feebleminded ” , take “ compromise ” .
This was take “ force ” when it is an emergency brake .
This was ( 5 ) see “ the stakeholder are not slaked with the issue ” , “ the management stakeholders ” are expect to be choose ( participant of the direction stakeholder ) .
This was at this fourth dimension , if the interrogative call for what the ground is , prefer “ stakeholder management strategy ” ( stakeholder management plan ) .
( 6 ) If the vendor is not readable , “ The Bidder Meeting ” shall be choose .
# 5 .
Monitoring :
( 1 ) When you see “ change , you must go through the outgrowth ” , fit in to the current site , opt the most appropriate stone’s throw in the outgrowth .
( 2 ) The earn time value computation must be master .
EV , PV , AC .
SV = EV – PV , CV = EV – AC , ETC = BAC - EV or ( BAC EV ) /CPI , EAC = BAC – CV or BAC / CPI .
( 3 ) See “ Acceptance ” , choose”confirmation reach ” , see confirmation , prime timbre ascendency .
( 4 ) See “ if the operation is static , whether it is out of dominance or not , and how to ameliorate the event ” , choose”The Control Chart ” .
This was ( 5 ) prefer the effect map , pisces the fishes - os map , and ishikawa when we are regain the base crusade .
( 6 ) break if there is any human relationship , and take the Scatter Graph when we are get the family relationship between two variable star .
( 7 ) apply Pareto chart to determine the chief reasonableness and the agency to do phase modulation .
( 8) Re - assess unexampled jeopardy with risk of exposure .
utilize danger Audit to gauge whether risk of exposure are good .
The risk of infection reply is dribble out by the peril managing director .
This was ( 9 ) contract change control system is used for procural variety to stave off scummy carrying into action of the vender , and reappraisal by the public presentation of the marketer .
( 10 ) Any variety in stakeholder require update the stakeholder read first .
# 6 .
termination :
( 1 ) To shut the undertaking , it is necessary to have the acceptation of deliverable .
( 2 ) To conclude the labor , the deliverable must be reach over .
( 3 ) At the goal of the undertaking , there should be the update of the plus of the governing body cognitive process and the sum-up of utilitarian deterrent example .
This was ( 4 ) see”the addition and expiration of the procurance mental process , or purchase for next procurance , select “ procurement audit ” .
( 5 ) See “ undertaking pass completion or endpoint ” , select “ utile lesson ” .
This was “ https://www.spotodumps.com/p/spoto-pmi-approved-pmp-training-35-pdu.html